Hi Subramanyam,

 

I understand that you want to create a shift pattern for a month using 3 shifts A, B, and C...This can be done by incorporating the 3 shifts into one PWS as shown in the screen shot:

 

ScreenHunter_217 Jun. 19 00.12.jpg

 

But, what you have done was given 3 different PWS for  3 different shifts..and the numbering was not proper...For example, the PWS A SFT is altogether different from the rest two in your configuration and week number was 001...that is fine...but the PWS B SFT is a different PWS by itself and should start with week 001 instead of 002 ...therefore the error 'please sort the sequential numbers in ascending order'

 

The generated work schedule for the above screen shot is as follows:

 

ScreenHunter_218 Jun. 19 00.18.jpg

 

Please award marks if useful.

 

Regards,

 

Santoshini