Hello Experts
We have an Engineer-to-Order implementation for our client. Accordingly procurement is done per project. Each Project issues its PRs which are then converted to POs and recieved into Project Stock.
While assigning the material to the Network activity in Project (using material component) the system uses the price found in the material master (MAP or STD) as a planned cost appended to the project.
Problem:
while procuring the material, when we receive it into Project Stock (Mvt 101 Q + ) the Moving Average Price in the material master does not get updated. this way all newly created material master will never have a moving average price, thus whenever we try to assign them to the project we receive an error message (Cost for Material Component ###Mat.Num### cannot be determined.
Question:
How can I get the system to update moving average price (for all types of stock) based on procurement for project stock.???