Re: How to map revision level materials to already created inspection plan?

$
0
0

Hi Naresh,

 

Each raw material is having different revision level, so i dont think creating one inspection plan will solve this issue.

You will have to create different inspection plans for each Revision level.

 

I have not done this before but my approach would be

 

1. Check how many revision levels are there (AEOI Table) Put AETYP = 41 and enter Material code in field "OBJEKT".

2. Bifurcate Materials as per their revision levels.

3. Create inspection plan for each revision level and assign particular Materials to these plans.

 

Amol.