Hi,
Thru one DTP, You can't load data to from two sources to one dso.
You need to use two dtps.
If you use process chain then you can add two dtps in parallel and finally do activation.
Activation step you need to connect from two dtps.
Like below.
| |
| |
DTP1 DTP2
\ /
\ /
\ /
DSO Activation.process step.
when we trigger/run DTP, data move to new table. once we click on activation then only data will load to active table other wise no hope. So same time data won't move to new and active table.
Thanks